jwelk.com

OTOW Water Treatment Plant no. 3

Jones Edmunds provided design services for a new 24.0-MGD water treatment plant, including raw water well pump assemblies, raw water transmission piping, two 1.5-million-gallon water storage tanks, and a finished-water transmission main. Mr. Welkenbach, as Project Architect, provided pre-project planning and developed architectural specifications and drawings for a competitive fixed-price bid contract that involved the complete design and construction details for the water treatment plant, featured in the Best of the Best list in the Associated Builder and Contractors of Florida 2010 Excellence in Construction Awards.